JTC Industrial Checker: 60/40 Rule, Power, Floor Loading and Subletting

Screen a B1 or B2 factory before you sign: the 60/40 rule, the 30% sublet cap, ELISE power thresholds, PE endorsements and food or GDPMDS use.

Compliance scorecard-
Use of the unit
    Rules on this card
    • 60/40: at least 60% of GFA for the core industrial use, at most 40% ancillary office or showroom.
    • Subletting above 30% fails. From 15 April 2024 a first unauthorised sublet forfeits 100% of the monthly sublet fee, up from 50%. Keep an anchor of at least 70% of GFA, and respect a 5-year assignment prohibition where the lease has one.
    • EMA electrical installation licence (ELISE) is required above 45 kVA, about 63 A three-phase, and for any hazardous trade at any load. Licensed Electrician up to 45 kVA, Licensed Electrical Technician up to 500 kVA, Licensed Electrical Engineer above 500 kVA.
    • A PE (Civil) endorses a machine over 400 kg, racking over 3.0 m high by 1.2 m deep, a floor load above the unit's rating, a mezzanine or a cold room. SCDF minor A&A or a Fire Certificate, and MOM factory notification or registration, follow from the works and the trade.
    • Food use belongs in an SFA approved food zone (the 1 December 2025 list). GDPMDS needs quarantine, released, recalled and cold-chain segregation. A Zero-GST warehouse needs a tenancy stamped in the operator's name and a TradeFIRST assessment.

    A pre-lease screen. JTC, URA, EMA, BCA, SCDF, MOM, SFA, HSA and Customs each issue their own approval. Checked 26 October 2026.

    On this page
    1. Calculator
    2. Run the card before the option
    3. Subletting after April 2024
    4. Power and structure
    5. Food, pharma, bonded stock
    6. The 60:40 rule, applied to an office
    7. What counts as ancillary
    8. A standalone office is not an industrial use
    9. The temporary dormitory exception
    10. Enforcement

    Key takeaways

    • At least 60% of GFA must be core industrial or warehouse use. Ancillary office and showroom stay within 40%.
    • Subletting is capped at 30% of GFA, the anchor keeps at least 70%, and an unauthorised sublet now forfeits 100% of the monthly sublet fee.
    • ELISE is required above 45 kVA, or for any hazardous trade. The electrician's grade steps up at 45 kVA and at 500 kVA.
    • A machine over 400 kg, racking over 3.0 m, or a floor load above the unit rating needs a PE (Civil).

    The numbers

    60/40 rule
    At least 60% core use, at most 40% ancillary
    Subletting
    30% cap, 70% anchor, 100% fee forfeited if unauthorised
    ELISE
    Above 45 kVA, or any hazardous trade
    LEW grades
    Electrician to 45 kVA, technician to 500, engineer above 500
    PE (Civil)
    Machine over 400 kg, racking over 3.0 m by 1.2 m, or floor overload

    Run the card before the option

    Type the share of the unit that will actually be factory or warehouse, the share you hope to sublet, the approved load in kVA and the floor load you need. Toggle machines, racking, food use and MedTech use. The card is a pass only if every hard rule passes.

    A pass is not a licence. It is the list of endorsements you still have to collect: EMA’s ELISE, the right grade of licensed electrical worker, a PE (Civil), SCDF if you are opening walls or adding a mezzanine, and MOM if you are manufacturing.

    Subletting after April 2024

    The 30% cap did not change. The penalty did. A first offence of subletting without approval forfeits the whole monthly sublet fee, not half of it. The anchor occupier still has to hold at least 70% of the GFA. A lease that still sits inside a five-year assignment prohibition cannot be assigned around these rules.

    Power and structure

    45 kVA is the ELISE line for an ordinary trade, and it is also the line between a licensed electrician and a licensed electrical technician. Hazardous trades need ELISE even when the load is small. 500 kVA is the line for a licensed electrical engineer.

    On structure, the triggers are practical: one machine over 400 kg, pallet racking taller than 3.0 m and deeper than 1.2 m, a mezzanine, a cold room, or a required floor load above the number in the building’s approved plans. Upper floors of flatted factories and ground floors of ramp-up B2 warehouses are not interchangeable.

    Food, pharma, bonded stock

    A central kitchen has to sit in an area on SFA’s list updated 1 December 2025. The food zone guide names the clusters. GDPMDS and a Zero-GST warehouse add their own physical layout, covered in the GDPMDS and Zero-GST guide. If the unit fails those, a lower rent does not fix it.

    The 60:40 rule, applied to an office

    URA’s use quantum, updated 6 June 2026 for both Business 1 and Business 2, says at least 60% of total industrial gross floor area is for industrial purposes. The remaining 40% may be ancillary. In a multi-user building the same split applies to the whole development and to each strata unit. URA’s own example of what must stay inside 40% of the unit is ancillary office and meeting rooms.

    Unit floor area Maximum ancillary office
    1,000 sq ft 400 sq ft
    2,000 sq ft 800 sq ft
    5,000 sq ft 2,000 sq ft

    The 60% has to be a real industrial use: manufacturing, repair, production, storage of the kind the zone allows, core media with the technical facilities URA describes, or an e-business use on URA’s list. A desk, a client meeting room and a reception are the ancillary share. Filling the unit with those, and calling the rest storage that never happens, fails the rule.

    JTC repeats the point when you ask to change the use. The new use must still leave at least 60% in industrial use, and JTC says you should not commit to the tenancy or the renovation before the outcome. JTC says that outcome comes within 10 working days. The approved-use page separates JTC’s consent from URA’s.

    What counts as ancillary

    On the B1 list the ancillary uses include an ancillary office, a showroom, a childcare centre, a workers’ dormitory, a meeting room, an industrial canteen and an ancillary display area. Selected commercial uses are limited to outlying areas. On the B2 list the ancillary uses include an ancillary office, a meeting room, a showroom, an industrial canteen and selected commercial uses. A shop, a restaurant, a commercial school or a bank sits in the White component, if the site has one. It is not a way to enlarge the 40%.

    The zone difference, including the 50 metre and 100 metre buffers, is on the B1 and B2 page.

    A standalone office is not an industrial use

    JTC’s subletting rules say the same thing in operational language. A sublet has to be for industrial use. Any office inside the sublet space has to support the manufacturing in that space. Office use on its own is not permitted. The subletting page has the 30% cap and the three-year limit for a non-related subtenant.

    A landlord’s brochure that says “office use” does not amend URA’s quantum. If the approved use of the unit is industrial, the 40% cap is the office you can defend.

    The temporary dormitory exception

    The 40% cap is not relaxed so that a unit can become an office. URA’s circular of 10 February 2023 raised the ancillary and secondary quantum from 40% to 49% to accommodate temporary workers’ dormitories, including the dormitory’s supporting amenities. The handbook still states that 49% figure for temporary workers’ dormitories. URA said the revision would be reviewed and might be removed. It is a dormitory allowance. It is not permission to take the extra 9% as office.

    Enforcement

    URA can refuse or condition a development application, and a use that is not the approved use needs a change of use. JTC, where it is landlord, can refuse the change-of-use application and can treat an unapproved sublet as a breach. JTC says that breach may end the lease or tenancy, or raise the sublet fee to as much as 100% of the assessed sublet rent. A lower rent does not cure either problem.

    Get an introduction

    Tell us what you need. The service below is set for this page and you can change it. Fiona replies on WhatsApp.

    Fiona Wang (PropNex, CEA R068552B) is a Singapore property agent. For services outside estate agency we introduce you to independent professionals; you choose and pay them directly. If a referral fee or related-party interest applies we will tell you before you engage.

    Questions on this topic

    Can I use half the factory as an office and showroom?

    No. URA caps ancillary office and showroom at 40% of the strata unit. The other 60% has to be the industrial use. On a 1,000 square foot unit that is at most 400 square feet of office.

    What is the JTC 60:40 rule?

    The quantum is URA's. At least 60% of the gross floor area is industrial use and at most 40% is ancillary, both for the whole development and inside each strata unit. JTC applies that rule when you change the use or sublet, and will not approve a sublet that is a standalone office.

    Can a B1 unit be used as a showroom?

    Only as an ancillary showroom inside the 40%. A showroom is on URA's ancillary list for B1 and B2. It is not the predominant use.

    What changed on 15 April 2024?

    JTC raised the penalty for a first unauthorised subletting offence. It now forfeits 100% of the monthly sublet fee, up from 50%. Approval in writing is the only safe path, and it still cannot exceed 30% of GFA.

    When do I need an electrical installation licence?

    Above 45 kVA, roughly 63 amps on three-phase, or at any load if the trade is dangerous or hazardous. Up to 45 kVA a licensed electrician is enough if the trade is not hazardous. Above 45 kVA you need a licensed electrical technician, and above 500 kVA a licensed electrical engineer.

    My machine weighs 500 kg. Is the floor rating enough?

    Weight and floor loading are separate tests. Anything over 400 kg needs a PE (Civil), even on a strong ground-floor slab. Upper-floor flatted factories are often only 5.0 to 7.5 kN per square metre. Ramp-up and ground-floor B2 units are often 12.5 to 25.

    Get a commercial shortlist

    Tell us the use, the size and when you need to move. We'll send offices, shophouses or industrial units that fit, with the reinstatement and fit-out questions flagged before you sign.

    Fiona Wang (Wang Ye), PropNex Realty Pte. Ltd.. CEA Reg. No. R068552B. Agency licence L3008022J.

    We'll reply on WhatsApp. Your details go only to our agent and are never sold. See our privacy notice.

    Sources

    Facts on this page were checked against these sources on 31 October 2026.

    1. JTC: Subletting your premises jtc.gov.sg, checked 31 October 2026
    2. URA: B1 use quantum, updated 6 June 2026 ura.gov.sg, checked 31 October 2026
    3. URA: B2 use quantum, updated 6 June 2026 ura.gov.sg, checked 31 October 2026
    4. URA: temporary workers' dormitories, 10 February 2023 ura.gov.sg, checked 31 October 2026
    5. EMA: Electrical installation licences ema.gov.sg, checked 31 October 2026
    6. SFA: Areas for licensed food establishments (updated 1 Dec 2025) sfa.gov.sg, checked 31 October 2026
    7. MOM: Factory notification and registration mom.gov.sg, checked 31 October 2026