Key takeaways
- There is no official dollar-per-square-foot rate for an office fit-out.
- Insignificant building works on BCA's First Schedule do not need a plan submission to BCA.
- Other building work needs a Qualified Person. Structural work needs a professional engineer and a permit.
- A rent-free period is a term you negotiate. No statute sets the number of months.
The numbers
- Official psf rate
- None. Get a quote
- BCA, minor works
- First Schedule works need no plan submission
- Other building works
- Qualified Person and plan approval
- Structural works
- Professional engineer and a permit
- Rent-free period
- Whatever the letter of offer says
The fit-out cost is whatever the specification costs in that building. A published range that cannot be opened and checked does not belong on this page. The rules that can be checked are who must approve the work, and who the lease says will pay for it.
What a quote has to cover
Ask the contractor to separate four lines, because they are not the same approval and not the same tax treatment.
| Line | Why it is separate |
|---|---|
| Loose furniture and equipment | Section 14N is renovation and refurbishment. Loose furniture follows capital allowance rules, which your tax agent applies |
| Partitions, finishes, cabling | Often the bulk of a tenant’s fit-out. Confirm whether BCA treats the item as insignificant |
| Air-conditioning, extra floor load, a new opening in a wall | Can become structural or fire-safety work |
| Reinstatement at the end of the lease | A cost of leaving, priced on the reinstatement calculator. It is not part of the fit-out you hope to keep |
Qualifying renovation and refurbishment is deducted under Section 14N, capped at S$300,000 for a relevant three-year period. The Section 14N guide has the periods and the exclusions. The cap is a deduction against taxable income. It is not cash from IRAS on the day you pay the contractor.
Rent-free periods
No statute sets a rent-free month for an office fit-out. If the landlord gives time to build, it is a sentence in the letter of offer. Write down whether rent, service charge and GST are all paused, or only the base rent, and whether that time counts as part of the lease term for stamp duty.
IRAS charges lease duty on the rent in the document. A rent-free stretch that is part of a longer term can still affect the duty if the overall term or a later extension changes the rent that is counted. Run the dates through the office lease stamp duty calculator using the rent the agreement actually charges in each month.
BCA and SCDF
BCA says some minor building works are insignificant building works under the First Schedule of the Building Control Regulations, and those do not need a plan submission to BCA. The owner still has to build safely and get any other authority’s approval. Unauthorised building work is an offence under the Building Control Act.
Anything that is not on that list goes in through a Qualified Person: an architect registered with the Board of Architects, or a professional engineer registered with the Professional Engineers Board, with a valid practising certificate. Before the building plan goes to BCA, the Qualified Person must have written permission from URA where planning permission is required.
Structural work is a further step. Only a professional engineer in the civil or structural discipline applies for structural plan approval. A permit, applied for jointly by the developer, the Qualified Person and the builder, is required before structural works start, except for insignificant building works.
SCDF is not BCA. URA’s change-of-use page says that after planning permission you still apply for the permits the use needs, and it names SCDF fire safety clearance as one of them. The Qualified Person is the person who tells you whether this fit-out needs a fire safety plan. This page does not quote an SCDF fee, because the fee depends on the submission.
Also read the management corporation’s by-laws and the landlord’s fit-out manual. BCA says owners must comply with other laws, including MCST by-laws. A plan BCA accepts can still be a breach of the lease.
Who pays, landlord or tenant
The lease decides. These are the questions to put in the letter of offer, in writing.
| Item | What to agree |
|---|---|
| Landlord’s works | The list, the standard, and the date they finish |
| Tenant’s works | What you may build, and what you must remove |
| Existing fit-out you take over | Whether you maintain it and whether you reinstate it |
| Rent-free or a fit-out contribution | The dollars, the months, and what happens if you leave early |
| Reinstatement | The standard, the notice, and whether a cash settlement is allowed |
A bare shell at a lower rent is not cheaper until the quote and the reinstatement of the office you are leaving are in the same sum. That comparison is what the lease calculator is for, using your figures rather than a borrowed price per square foot. The deposit page covers what a landlord can keep back at the end, which is also a lease question rather than a fixed statutory sum.
Get an introduction
Tell us what you need. The service below is set for this page and you can change it. Fiona replies on WhatsApp.
Thank you
Fiona has your introduction request and will reply on WhatsApp. For anyone other than her estate agency work, you choose the professional and you pay them directly.
WhatsApp FionaQuestions on this topic
What are office fit-out costs?
They are the cost of making the unit usable: partitions, finishes, mechanical and electrical work, and fire safety work. Singapore has no published statutory rate per square foot. Agency guides that quote one were not used here, because the underlying guide was not available to check. Price the specification with a contractor, then compare that quote with a fitted unit on the lease calculator.
How much does it cost to renovate an office in Singapore?
The honest answer is the quote for that unit. A coat of paint and loose furniture is a different job from a new air-conditioning system or a new staircase. BCA's question is whether the work is an insignificant building work. If it is not, a Qualified Person submits plans before the work starts.
What is a small office fit-out cost?
Small does not put the work outside the Building Control Act. The same First Schedule test applies. A short lease also changes who should pay: a tenant who has to reinstate may not want to fund a landlord's improvement. That split belongs in the letter of offer.
Is there an office fit-out cost calculator?
PropertyHQ does not invent a price per square foot. The lease calculator compares a bare unit and a fitted unit once you type in the quotes you have. Section 14N, if the work qualifies, is a tax deduction capped at S$300,000 for a relevant period, not a grant that pays the contractor.
Get a commercial shortlist
Tell us the use, the size and when you need to move. We'll send offices, shophouses or industrial units that fit, with the reinstatement and fit-out questions flagged before you sign.
Sources
Facts on this page were checked against these sources on 31 October 2026.
- BCA: building works not requiring approval www1.bca.gov.sg, checked 31 October 2026
- BCA: building plan submission www1.bca.gov.sg, checked 31 October 2026
- BCA: structural plan submission www1.bca.gov.sg, checked 31 October 2026
- URA: change of use, including later SCDF clearance ura.gov.sg, checked 31 October 2026
- IRAS: renovation and refurbishment deduction, Section 14N iras.gov.sg, checked 31 October 2026